Full Screen
Map - Zoom In
Map - Zoom Out
Panoramic Images
Preloader

About the Project

We are developing a project which will seek to create a joint connection between SSE Renewables Tangy IV Wind Farm and Belltown Power Cnoc Buidhe Wind Farm, both are located approximately 10km north-west of Campbeltown, in Argyll. The overall aim of our project is to connect these wind farms to the existing infrastructure at, or near Carradale substation.

Tangy IV and Cnoc Buidhe were originally two single circuit wood pole connections, both close to Lussa Loch and connecting at, or close to, Carradale. However, following an application by the developer to increase the output for the Cnoc Buidhe Wind Farm the required Transmission structure changed from an initial trident wood pole to a single circuit tower.

The project team have reviewed potential solutions for the connection of both wind farms from an engineering, environmental, land and cost perspective. The most efficient solution involves a shared use double circuit overhead line tower connection for both Tangy IV and Cnoc Buidhe wind farms.

This will mean that there will be one construction plan which will lessen the impact of the wind farm on the local environment and communities.

SSEN Transmission are proposing to construct a new 132 kilovolt (kV) connection with a combination of overhead line (OHL) and underground cables (UGC) between the Tangy IV Wind Farm and Cnoc Buidhe Wind Farm substations and the existing Carradale Grid Supply Point (GSP) - a distance of approximately 21.5 km.

The developer of Tangy IV Wind Farm has submitted an application to the Scottish Government under Section 36 of the Electricity Act 1989 and has been consented for a 100-megawatt (MW) Wind Farm. The Cnoc Buidhe Wind Farm are aiming to submit their S36 application in 2024. They have an indicative capacity of 198MW comprising up to 30 turbines. A connection date of May 2029 is currently planned for Cnoc Buidhe and April 2029 for Tangy IV.

Under the terms of Schedule 9 of the Electricity Act 1989, SSEN Transmission is therefore obliged to connect the Tangy IV Wind Farm and Cnoc Buidhe Wind Farm to the transmission network by the contracted connection date.

The proposed project would involve:

1. Approximately 8.5km of an Underground Cable between the Tangy IV Wind Farm (5.5km) and Cnoc Buidhe Wind Farm (3km) substations through the proposed Cnoc Buidhe Wind Farm to the terminal overhead line connection point, north of Collusca Water.

2. Approximately 13km of 132kV double circuit overhead line supported by steel lattice towers, from north of Collusca Water to northwest of Carradale Substation.

3. Approximately 650m underground cable to the existing Carradale Substation.

4. An extension to Carradale Substation to connect Tangy IV Wind Farm and Cnoc Buidhe Wind Farm to the grid whilst ensuring all protection equipment is installed in the event of a fault.

To submit feedback please click here.

Portal Navigation

The information below is intended to assist with navigating the 3D Portal, however there is an Interactive Portal User Guide, which you can access by clicking here

The Map


In order to view the visualisations and navigate the portal, please start by clicking on any of the cameras on the adjacent map. They are situated next to their relevant viewpoints to allow access to areas of interest.

Should you prefer to view the map in satellite, this can be done by clicking the ‘Satellite’ tab at the top right hand corner of the map.

Once you have clicked on a viewpoint, if you want to return to the full map at any point, please click on the project map icon situated down the left-hand side of the map – it is a location pin icon on top of a grid.

If you are viewing a video and would like to return to the overview map, the project map icon is situated at the top right-hand corner of the screen.

Visualisations


Once you click on a visualisation, you will be presented with two tabs across the top middle of the screen; ‘Existing’ and ‘Proposed’

If you click on the existing tab, it will show you the area as it currently stands, without the proposed Cambushinnie project.

If you click on the proposed tab, it will show you the proposed Cambushinnie project.